Thursday, 8 January 2009

Precast concrete pile







Precast Reinforced Concrete Pile

The most common pile type in many parts of the world, such as Scandinavia, is the precast concrete pile. Precast concrete piles are commonly manufactured in square and ranging from about 250 mm to about 450 mm, with a maximum section length of up to about 20 m. Other pile sections exist and may include hexagonal, circular, triangular and H shapes.
The piles have generally been driven with a drop hammer of 3 to 4 tons, although in recent years, hydraulic hammers have become very common for driving precast concrete piles. I some countries, diesel hammers and occasionally also vibrators are used. Maximum allowable axial loads can be up to about 1 000 kN. The length of pile sections is often dictated by practical considerations including transportation, handling problems in sites on restricted area and facilities at the casting yard.
Precast concrete piles can be constructed either in the factory or on site. The quality of the pile is very much affected by the construction and production process. A typical section of a Swedish precast concrete pile is shown.
Extending precast piles without joints is a lengthy process. It requires breaking down the projecting pile head to provide a suitable lap for the steel reinforcement and casting concrete to form the joint. Piles can also be connected by epoxy to form the joint. Good alignment of the pile sections is required to prevent excessive bending stresses developing on subsequent re-driving.
The pile length can be equipped with prefabricated joints. Other splicing methods commonly adopted include welding of steel end plates or the use of epoxy mortar with dowels.
Precast concrete piles are not suitable for soil deposits containing a significant amount of boulders. In such cases, the pile may be equipped with a
pile shoe, which protects the pile tip during hard driving.

Installation of Bored Piles

Installation of Bored Piles
Step 1 --- Excavation of Pile Shaft
The bored pile equipment set including hydraulic oscillator, hydraulic vibrator, hammer grab and rock chisel used in this project is very common and being widely used for shaft excavation.

a-Set out the correct position of the bored pile on site.
b-Excavate about 3 - 4m of the pile to remove shallow obstructions and then backfill, wherever necessary.
c-Install the bottom section of temporary casing of required diameter into the ground by oscillating and jacking or by vibrating motion exerted by the oscillator and the vibrator respectively.
d-Set up hydraulic oscillator or vibrator in conjunction with a crawler crane.
e-Excavate within the casing by hammer grab and redrive the steel casing simultaneously by using the heavy duty casing oscillator / vibrator. Rock chisel in various types will be employed for removal of obstruction or hard materials during the above process.
f-Extend the steel casing by bolting or welding on additional casing during the excavation.
g-Water will be pumped into the casing during excavation and constant water head will be maintained so as to prevent any ingress of material from the bottom of casing.
h-Verticality of the casing will be monitored by means of spirit level from time to time.
i-Continue the above procedure until the founding level of pile has been reached .
j-Pile base enlargement will be formed by employing a bellout chisel or a reverse-circulation drill as indicated in the working drawings.
Step 2 --- Cleaning of Pile Shaft
Final cleaning will be carried out by the air-fitting method using high pressure air compressors. The slime and muddy water within the casing will be cleared and delivered into a desilting tank before discharge.
Step 3 --- Tremie Concreting

a-The pile shaft will be concreted by "Underwater Tremie Technique". The tremie pipe sections will be inserted and be jointed until it reaches the bottom of pile shaft. Concrete will be poured into the tremie pipe by using a concrete skip. Concreting will be carried out in one continuous operation until the required level has been reached.
b-As concreting proceeds, the level of the concrete relative to the ground level will be monitored by measuring with weighted tape after each skip of concrete is placed.
c-The base of the tremie pipe will be kept with a minimum depth of approximate 1 to 2m below the surface of the concrete.
d-The temporary casing will be extracted simultaneously by the oscillator in the course of concreting. A head is always maintained between the top of concrete and the bottom of steel casing.
Step 4 --- Installation of Reinforcement
After the completion of concreting, dowel bars of required length and numbers will be installed into the pile shaft and down to the predetermined level before the extraction of bottom steel casing.

Step 5 --- Backfill After Completion

The bottom section of steel casing will be left in place above the concrete surface and will be extracted until the concrete is set.
Suitable soil will be used to backfill the excavation up to ground level after removal of the bottom casing.

Installation of steel H- piles

Installation of Steel H-piles
Step 1 --- Installation Procedures
a-Set out the steel pile location correctly on site.
b-Excavate about 3-4 m at pile location to remove shallow obstruction and then backfill, whenever necessary.
c-Set up the diesel hammer/drop hammer in conjunction with a pile driver.
d-Erect and install the bottom section of steel pile required size into the ground by driving with the diesel hammer/drop hammer.
e-Extend the pile by welding on additional section during driving.
f-Verticality of the pile section will be monitored by means of spirit level from time to time.
g-Continue the above procedure until the pile has been driven to final set according to the Final h-Set Table in the piling plans.
A follower will be used, when necessary, to drive the pile into the ground for final set where the cut-off level is deep.
i-At a particular pile position, where deep boulder obstructions are encountered during pile driving, extract the steel pile and drive a steel tubular pile down to punch through obstructions or use a 'Down-The-Hole' hammer to predrill through the boulder layer before the reinstallation of steel H-pile.
Step 2 --- Relationship Between H-pile & Concrete Pile
In order to ascertain the adequacy of the driven concrete pile, a dynamic formula, Hiley's Formula, will be applied to access the safe loading capacity of the pile.

Step 3 --- Monitoring Proposal
In order to ensure no adverse effects imposed on the adjoining buildings and structure during construction, the following precautionary measures and limiting criteria, to be monitored throughout the construction period, are recommended :
a-Settlement checkpoints and other monitoring devices are to be installed prior to the commencement of construction works.
b-Initial monitoring results should be submitted to the Governmental Department prior to the commencement of works.
c-The checkpoints and standpipe piezometers shall be monitored regularly during the construction period and duplicate copies of the monitoring results should be submitted to the Governmental Department on a regular basis and be kept available on site for inspection at all times.
d-Should the settlement at those checkpoints be found excessive during the course of works, the works should be suspended and the A.P., the Governmental Department should be notified immediately. Remedial proposal to safeguard the affected structure shall be submitted to the Engineer for approval.
e-Drawdown of water table in standpipes should not be greater than the specific value during the course of work.
f-All Monitoring devices should be maintained in good order during the works.
Step 4 --- Method Statement for Passing through Bouldery Obstructions During Pile Driving
a-In order to ensure no adverse effects imposed on the adjoining buildings and structure during construction, the following precautionary measures and limiting criteria, to be monitored throughout the construction period, are recommoned :
b-Where shallow boulder obstructions are expected or encountered during pile driving, a backhoe excavator will be used initially to excavate to remove bouldery obstructions about 6-7 m beneath ground surface.
c-At a particular pile position, where bouldery obstructions are encountered during pile driving at a depth beyond the reach of the arm of the backhoe excavator, extract the H-piles and a steel tubular pile ( or a heavier steel H-section ) will be driven down as to punch through the bouldery obstructions before re-installation of the H-pile.
d-Where the punching method cannot practically penetrate through the boulders, withdraw the pile and break the boulder obstructions with 470 dia. 'Down-the-hole' hammer to predrill through the boulder layer before re-installation of the H-piles and backfilled the hole with soil for pile driving.
e-The pile is then pitched and driven to final set according to the final set tables.

Layth on the site


Layth on the site

pile foundation







Driven foundations

Pipe piles being driven into the ground.
Prefabricated piles are driven into the ground using a pile driver. Driven piles are either wood, reinforced concrete, or steel. Wooden piles are made from trunks of tall trees. Concrete piles are available in square, octagonal, and round cross-sections. They are reinforced with rebar and are often prestressed. Steel piles are either pipe piles or some sort of beam section (like an H-pile). Historically, wood piles were spliced together when the design length was too large for a single pile; today, splicing is common with steel piles, though concrete piles can be spliced with difficulty. Driving piles, as opposed to drilling shafts, is advantageous because the soil displaced by driving the piles compresses the surrounding soil, causing greater friction against the sides of the piles, thus increasing their load-bearing capacity.

Pile foundation systems
Foundations relying on driven piles often have groups of piles connected by a pile cap (a large concrete block into which the heads of the piles are embedded) to distribute loads which are larger than one pile can bear. Pile caps and isolated piles are typically connected with grade beams to tie the foundation elements together; lighter structural elements bear on the grade beams while heavier elements bear directly on the pile cap.

Drilled piles

A pile machine in Amsterdam.
Also called drilled piers or Cast-in-drilled-hole piles (CIDH piles) or Cast-in-Situ piles. Rotary boring techniques offer larger diameter piles than any other piling method and permit pile construction through particularly dense or hard strata. Construction methods depend on the geology of the site. In particular, whether boring is to be undertaken in 'dry' ground conditions or through water-logged but stable strata - i.e. 'wet boring'.
'Dry' boring methods employ the use of a temporary casing to seal the pile bore through water-bearing or unstable strata overlying suitable stable material. Upon reaching the design depth, a reinforcing cage is introduced, concrete is poured in the bore and brought up to the required level. The casing can be withdrawn or left in situ.
'Wet' boring also employs a temporary casing through unstable ground and is used when the pile bore cannot be sealed against water ingress. Boring is then undertaken using a digging bucket to drill through the underlying soils to design depth. The reinforcing cage is lowered into the bore and concrete is placed by tremmie pipe, following which, extraction of the temporary casing takes place.
In some cases there may be a need to employ drilling fluids (such as bentonite suspension) in order to maintain a stable shaft. Rotary auger piles are available in diameters from 350 mm to 2400 mm or even larger and using these techniques, pile lengths of beyond 50 metres can be achieved.

Underreamed piles
Underream piles have mechanically formed enlarged bases that have been as much as 6 m in diameter. The form is that of an inverted cone and can only be formed in stable soils. In such conditions they allow very high load bearing capacities.

Augercast pile
An augercast pile, often known as a CFA pile, is formed by drilling into the ground with a hollow stemmed continuous flight auger to the required depth or degree of resistance. No casing is required. A high slump concrete mix is then pumped down the stem of the auger. While the concrete is pumped, the auger is slowly withdrawn, lifting the spoil on the flights. A shaft of fluid concrete is formed to ground level. Reinforcement placed by hand is normally limited to 6 metres in depth. Longer reinforcement cages can be installed by a vibrator, or placed prior to pouring concrete if appropriate specialized drilling equipment is used.
Augercast piles cause minimal disturbance, and are often used for noise and environmentally sensitive sites. Augercast piles are not generally suited for use in contaminated soils, due to expensive waste disposal costs. In ground containing obstructions or cobbles and boulders, augercast piles are less suitable as damage can occur to the auger. An alternative to augercast piles in contaminated soils areas would be a DeWaal pile (a European patented process) in which you use a four foot auger and above this is straight pipe smaller than the diameter of the auger bit. This process minimizes spoils and is usually used in petrochemical plants.

Pier and grade beam foundation
In most drilled pier foundations, the piers are connected with grade beams - concrete beams at grade (also referred to as 'ground' beams) - and the structure is constructed to bear on the grade beams, sometimes with heavy column loads bearing directly on the piers. In some residential construction, the piers are extended above the ground level and wood beams bearing on the piers are used to support the structure. This type of foundation results in a crawl space underneath the building in which wiring and duct work can be laid during construction or remodeling.

Specialty piles

A micropile installation.

Micropiles
Micropiles, also called mini piles, are used for underpinning. Micropiles are normally made of steel with diameters of 60 to 200 mm. Installation of micropiles can be achieved using drilling, impact driving, jacking, vibrating or screwing machinery.[1]
Where the demands of the job require piles in low headroom or otherwise restricted areas and for specialty or smaller scale projects, micropiles can be ideal. Micropiles are often grouted as shaft bearing piles but non-grouted micropiles are also common as end-bearing piles.

Tripod piles
The use of a tripod rig to install piles is one of the more traditional ways of forming piles, and although unit costs are generally higher than with most other forms of piling, it has several advantages which have ensured its continued use through to the present day. The tripod system is easy and inexpensive to bring to site, making it ideal for jobs with a small number of piles. It can work in restricted sites (particularly where height limits exist), it is reliable, and it is usable in almost all ground conditions.

Sheet piles
Sheet piling is a form of driven piling using thin interlocking sheets of steel to obtain a continuous barrier in the ground. The main application of steel sheet piles is in retaining walls and cofferdams erected to enable permanent works to proceed.

Soldier piles

A soldier pile wall using reclaimed railway sleepers as lagging.
Soldier piles, also known as king piles or Berlin walls, are constructed of wide flange steel H sections spaced about 2 to 3 m apart and are driven prior to excavation. As the excavation proceeds, horizontal timber sheeting (lagging) is inserted behind the H pile flanges.
The horizontal earth pressures are concentrated on the soldier piles because of their relative rigidity compared to the lagging. Soil movement and subsidence is minimized by maintaining the lagging in firm contact with the soil.
Soldier piles are most suitable in conditions where well constructed walls will not result in subsidence such as over-consolidated clays, soils above the water table if they have some cohesion, and free draining soils which can be effectively dewatered, like sands.
Unsuitable soils include soft clays and weak running soils that allow large movements such as loose sands. It is also not possible to extend the wall beyond the bottom of the excavation and dewatering is often required.

Suction Piles
Suction piles are used underwater to secure floating platforms. Tubular piles are driven into the seabed (or more commonly dropped a few metres into a soft seabed) and then a pump sucks water out the top of the tubular, pulling the pile further down.
The proportions of the pile (diameter to height) are dependent upon the soil type: Sand is difficult to penetrate but provides good holding capacity, so the height may be as short as half the diameter; Clays and muds are easy to penetrate but provide poor holding capacity, so the height may be as much as eight times the diameter. The open nature of gravel means that water would flow through the ground during installation, causing 'piping' flow (where water boils up through weaker paths through the soil). Therefore suction piles cannot be used in gravel seabeds.
Once the pile is positioned using suction, the holding capacity is simply a function of the friction between the pile skin and the soil, along with the self-weight and weight of soil held within the pile. The suction plays no part in holding capacity because it relieves over time. The wall friction may increase slightly as pore pressure is relieved. One notable failure occurred (pullout) because there was poor contact between steel and soil, due to a combination of internal ring stiffeners and protective painting of the steel walls.

On the site


On the site 6-1-2009

Deep foundation


Deep foundation

A deep foundation is a type of foundation distinguished from shallow foundations by the depth they are embedded into the ground. There are many reasons a geotechnical engineer would recommend a deep foundation over a shallow foundation, but some of the common reasons are very large design loads, a poor soil at shallow depth, or site constraints (like property lines). There are different terms used to describe different types of deep foundations including piles, drilled shafts, caissons, and piers. The naming conventions may vary between engineering disciplines and firms. Deep foundations can be made out of timber, steel, reinforced concrete and pre-tensioned concrete. Deep foundations can be installed by either driving them into the ground or drilling a shaft and filling it with concrete, mass or reinforced.

photo from the site


Photo from the site on 6-1-2009